For installation-only bids, I would start with a task-based worksheet rather than carrying forward an old regional price per cabinet. Separate receiving/unloading, layout, cabinet setting, fillers and scribes, trim, hardware adjustments, protection, and the final punch visit. Record the crew hours and scope assumptions against each task.
For future jobs, compare estimated crew hours with recorded hours for the same task. Keep travel, restricted access, occupied-site work and return visits visible rather than burying them in a per-piece rate. A rate from another installer is difficult to compare unless both scopes include the same work.
A small spreadsheet can do this: item/location, quantity, unit, labor hours per unit, extended hours, material allowance, and scope notes. Build the initial labor inputs from your own records or a small measured trial, then revise them as actual job data becomes available. Software helps organize those inputs, but it cannot establish your crew productivity.
Also distinguish crew-hours from elapsed hours: two people working four hours contribute eight labor hours. Separate the installation takeoff from your pricing assumptions so drawing revisions can be reviewed without obscuring the labor basis.
Malik Waqas
F&K Estimatings — construction estimating and quantity takeoff